Work about to begin on level crossings in Werribee

Site establishment works are about to get underway to remove two level crossings west of Melbourne near Werribee.

This month, site office and are preparation works will begin at the Werribee Street level crossing and at the Old Geelong Road level crossing in Hoppers Crossing.

At Werribee Street, the Level Crossing Removal Project will construct a new rail bridge over Werribee Street. Works in April and May will involve setting up site offices on Cottrell Street, locating utilities including electricity and water and removing trees and vegetation within the project area. Work will then begin on piling for bridge foundations and a temporary track, to ensure freight services can continue running on the Geelong Line.

Similar works will get underway at the Hoppers Crossing Site to prepare for the construction of a road bridge and pedestrian overpass above the rail line. The Hoppers Crossing station carpark will be relocated while works are progressing.

These works notifications following the confirmation of designs for the two level crossing removals. McConnell Dowell, Arup, Mott MacDonald, and Metro Trains Melbourne will be delivering the work, in addition to the Cherry Street level crossing work nearby.