Below Rail Infrastructure, Passenger Rail, Rail Supply, Signalling & Communications

Contracts awarded for track and systems works on CRL

Two contracts have been awarded for the delivery of works for Auckland’s City Rail Link.

Known as C5 and C7, the contracts have been awarded to delivery consortium Link Alliance and are within the existing project budget.

C5 primarily involves the connection between the new line from Britomart, via Aotea and Karangahape, to the existing line at Mt Eden. Where the CRL meets the North Auckland Line at Mt Eden, the twin track split into two branches, eastbound and westbound, said Francois Dudouit, project director for the Link Alliance.

“This requires changing the vertical alignment of the NAL tracks and partially the horizontal alignment, meaning replacement of tracks and overhead line equipment (OHLE) on more than 1km of the North Auckland line,” he said.

“It also requires retaining walls to transition from the existing NAL track level to the CRL line – a 3.5 per cent slope. More than 1,000 piles, diaphragm and sheet pile walls will be needed to build these retaining structures and the two cross-over structures to connect to the NAL upmain.”

Road and pedestrian bridges at a number of level crossings will also be built, including at Normanby Road, Fenton Street, and Porters Avenue, to improve cyclist and pedestrian safety.

The C7 contract covers the Systems Integration, Testing and Commissioning components of the CRL project. These include trackslab, track, overhead line, signalling, control systems, communications systems, control room fit-out and building work, and trackside auxiliaries. Work also includes integrating the new line and systems with the legacy systems on the Auckland rail network.

Dudouit said that work to connect the various components of the project is already occurring.

“Integration of the C5 and C7 teams into the Link Alliance is well underway across multiple workstreams including civils, programme and cost control. Early works such as utility relocations and establishing single-line running are already taking place as part of an integrated programme to deliver the City Rail Link to Aucklanders in 2024.”

As these elements of the project require involvement from various stakeholder from the current network, such as the transport authority, Auckland Transport, close working relationships have been established.

“KiwiRail and Auckland Transport, and their supply partners, are formally engaged for the City Rail Link project through stakeholder partnership agreements. On a day-to-day basis, staff from both Auckland Transport and KiwiRail work in the Link Alliance offices to maximise collaboration opportunities, as part of an established interface and relationship management programme,” said Dudoit.