Three level crossings to be upgraded North East Rail Line

The Australian Rail Track Corporation (ARTC) has confirmed that works will continue over the Easter weekend to upgrade the North East Rail line in Victoria.

The three level crossings upgraded over the long weekend are at Racecourse Rd, Chiltern, Federation Way at Bowser (Wangaratta North), and Bourke Rd at Bowser (Wangaratta North).

These improvements are on top of the 19 level crossings already upgraded in regional Victoria, including at West Wodonga, Wangaratta, and Barnawartha. Additionally, 16 rail bridges have been improved as part of the $235 million project.

“Teams have worked systematically south after major work started in Wodonga with four more level crossing renewals scheduled for April,” said ARTC general manager major projects Ed Walker.

“Work will start at 6pm on Sunday 12 April to improve these level crossings and we thank the community for their patience with changed traffic conditions in place and increased vehicle movements in the area.”

The project has focused on having benefits during the construction phase flow through to regional communities, with a major site office located in Wangaratta employing locals and engaging 32 North East Victorian suppliers.

Over 100,000 tonnes of ballast have been added to the track for depth improvement, mudhole removal, bridge works, and level crossing renewals.