Below Rail Infrastructure, Passenger Rail, Products & Technology, Rail Supply

Rethinking rail machinery: KH1 providing solutions with the Zagro Unimog

The complexity of the Melbourne Metro Tunnel project requires a new approach when it comes to the delivery of materials and equipment. KH1 solved that with the Zagro Unimog.

In mid-July 2018, then-Victorian Minister for Public Transport Jacinta Allan announced the successful consortium that would build the critical link between the underground sections of Melbourne’s new Metro Tunnel and the existing rail network.

This announcement kicked off a package of works that would include both tunnel entrances at South Yarra and Kensington, as well as improvements to the adjoining Sunbury lines. Working within and beside the operating rail corridor in the inner suburbs of Melbourne meant that the project had an extra layer of complexity, meaning that every effort had to be made to ensure the project ran smoothly and efficiently.

The successful consortium, Rail Infrastructure Alliance (RIA), which comprised John Holland, CPB Contractors, and AECOM, looked to local rail suppliers who were innovating in the delivery of similarly complex projects. They found one in the case of Campbellfield- based KH1.

Daniel Mociak, managing director of KH1, could see that the project required smart thinking when it came to getting materials in and out of the worksites.

“RIA had a lot of restraints around getting materials, plant, people, and equipment in and out of their locations. This is really inner-city Melbourne and once they get into the shutdown, they have a lot of workgroups that can’t get out until the shutdown is over. They can’t constantly move equipment in and out so they have to get a lot of equipment in one lot and then be very flexible about how they can move around.”

Mociak and KH1 were brought in by RIA to look at how the project team could move a variety of pieces of machinery into the worksite. The solution that they came up with was the Zagro Unimog.

“The main benefit is the shunting capacity,” said Mociak.“That machine itself can pull up to 600 tonnes and other Unimogs that we could deliver are able to pull up to 1,000 tonnes with an increased wagon brake system.”

The Zagro Unimog road-rail vehicle can provide shunting and project logistics tasks. The relatively compact vehicle has the capacity to tow rail trailers weighing up to 125 tonnes at speeds of up to 30km/h. The removeable wagon brake system enables the Unimog to shunt up to 600 tonnes. Since being delivered in 2020, the system has already been put to good use.

“RIA needed to bring in plant, equipment, and excavators,” said Mociak. “They have a series of trailers that they were going to attach to the back of the Unimog to bring in all sorts of construction equipment and materials.”

The Unimog could then return to the access points, taking with it unneeded materials, spoil and other rubbish. RIA rail systems delivery manager Rimmy Chahal, pointed out the benefits of using the Unimog as it has reduced the number of single plant movements.

“The Unimog has largely been used to transport plant, equipment and materials in access-constrained rail corridors. This is in contrast to conventional transport methods of rubber tyred plant on railway tracks or a series of rail-bound plant to undertake this task. With the Unimog, we are able to transport large volumes in a single move from the access point to the work location along the corridor in a safe and controlled manner.”

The Unimog is used along with a five trailer consist to transport concrete, steel gantry structures, pits, conduits, quarry material, spoil disposal bins, cable, rail, sleepers and turnout components, among other materials. Being able to tow a lengthy consist also has benefits when it comes to safety.

“The 5-trailer combination also provides an additional benefit of safely and securely transporting long and bulky items such as turnout switch blade assemblies, which would normally overhang on conventional transport trolleys. Other uses have also included the deployment of site amenities and lighting towers to constrained areas improving safety and work environment conditions for our workforce,” said Chahal.

Another challenging requirement was the need to transport concrete along the rail corridor where access was restricted. Traditional methods of carrying in concrete on rail-bound excavators would require numerous movements to complete a single gantry foundation and had a greater risk of quality and safety issues. With RIA needing to deliver over 550 foundations for overhead and signal structures, a different solution was required.

“RIA and KH1 worked together to configure a skid-based concrete transport solution that can be mounted on rail bound plant. For example – on a trailer towed by Unimog to transport large volumes of concrete from access point to work location. This solution enables the complete pouring of a gantry foundation in one movement rather than numerous movements as required using conventional means,” said Chahal.

This solution involved the BlendMX8, a mobile concrete agitator first designed for the Monte Ceneri base tunnel in Switzerland.

“The BlendMX8 connects on to rail trailers and rail wagons via container lock and is then able to transport concrete in and out of the rail corridor without having to drive concrete trucks on top of wagons,” said Mociak. “It gives RIA flexibility in having the concrete on demand whenever they want it and then able to deliver the concrete via a conveyor belt and chute which can place the concrete up to five metres away from the rail.”

With the equipment expected to be used soon, Chahal is looking forward to seeing it in action.

“This unit is currently undergoing commissioning and RIA is very excited to put it into use over the coming months.”

kh1
The Unimog enables new ways of working in a confined rail environment.

A NEW APPROACH
The approach required for a project as complex as the Melbourne Metro Tunnel has driven innovation in the delivery of plant and equipment. Mociak noted that previous approaches of using wagons and locomotives would not only be prohibitive from a cost basis but limit any flexibility. The ability of machines such as the Unimog to move between road and rail while providing the required shunting capacity is one example of this new thinking.

“In the last couple of years, KH1 has put a lot of emphasis in developing technology and innovation for project logistics,” said Mociak.

The constrained environment of the Melbourne Metro Tunnel project meant that new ideas had to be sought out, said Chahal.

“With urbanisation of the areas around railway lines, the ease of access to rail corridors to conduct maintenance, upgrades, renewals and project works is becoming increasingly restricted and challenging. We can no longer rely on driving along the rail corridor to get to the work location. Accordingly, we now undertake careful and detailed planning to manage the site logistics and work sequence to overcome access constraints and challenges,” he said.

With complex tunnelling projects underway around Australia and New Zealand, the planning and logistics behind the project needs to be increasingly sophisticated.

“The major metropolitan based projects that have come to the front in the last couple of years is a big change in the rail industry, so to support these megaprojects, we’re looking at how we can add value of benefit to the project through innovative movement of materials, plant, equipment, and people,” said Mociak.

In these cases, the solution is not so much about the individual pieces of equipment that are involved, but the careful planning and logistics that supports their operation. With targets being set ever higher, new methods are being implemented, said Chahal.

“Construction contractors are being set ambitious KPIs to minimise the impact of construction on community, stakeholders and rail services. These performance targets drive a strong industry focus on continuous improvement and innovation in how we deliver our works whilst minimising associated disruption. RIA’s use of the Unimog is a perfect example of innovation in action.”

Knowing how the machinery, whether it be the Unimog or concrete agitator, can be best utilised can make a world of difference.

“Because they’re highly complex projects with large numbers of work groups, the logistics of getting materials in and out is one of the hardest parts of the project and they’re also the thing that can really hurt the project if you get it wrong. Getting it right can have some significant benefits,” said Mociak.

For groups working in rain on underground tunnelling projects, all materials have to be brought in at the beginning of a shift, if anything is forgotten it stays at the surface. With each work group depending on the one in front of it, any issues can be passed down, limiting productivity and efficiencies

Back in Melbourne, it has been the partnership approach between KH1, its partner suppliers and John Holland that is making the project successful.

“The equipment was delivered over a 10-month period and representatives from John Holland travelled to Germany to be there for the factory acceptance testing,” said Mociak. “We had a lot of input from all parties during the design period and a lot of collaboration from KH1, John Holland and Zagro.”

To prepare the Unimog for use by the RIA consortium, KH1 ensured that it was provided to specification and the requirements of the project. Documentation ran to hundreds of pages in length to enable the machine to be used in the most productive manner.

“We bring knowledge of the local Australian requirements, standards, compliance, certification, and commissioning process to the table while understanding the product that we have available to us and then being able to adapt it to those requirements,” said Mociak.

Putting in 15 years of experience in the Australian rail industry into the delivery of the machinery for RIA has enabled the Unimog to be used for a wide range of purposes, perhaps more than what was even envisaged before the machine arrived on site.

KH1 is also bringing this approach to the maintenance of railway networks. The company is working with German rail equipment manufacturer Robel to deliver new ways of working to the Australian rail maintenance market. Machines such as the Mobile Maintenance Train can provide a significant step change in the way we work in the rail corridor with full coverage for workers on the rail track in addition to all equipment needed for the job. Ultimately, said Mociak, this is about delivering three core outcomes.

“It’s about innovation, safety, and efficiency.”