PTA Radio Systems Replacement project falls victim to US-China trade war

The consortium delivering the digital radio systems project in Perth has fallen apart.

An alliance of Huawei Australia and UGL (HUGL) won the contract to upgrade radio communications for Western Australia’s Public Transport Authority (PTA) in 2018, however on March 27, 2020 WA Minister for Transport Rita Saffioti announced that the current contract will no longer proceed.

The HUGL consortium fell victim to increasing trade restrictions placed on Chinese exports by the US government, with restrictions imposed in August 2019 cited by the WA government as the tipping point.

In 2017, the WA government announced the $120 million project, which would involve installing new towers and poles with digital-friendly infrastructure, to enable the replacement of the current analogue radio system with a digital one. This involved all radio devices in trains, security vehicles, and handheld radios. Moving to a digital system would allow for data as well as audio to be transmitted by radio. Future Automatic Train Control systems, which PTA has aimed to install as part of the Metronet project, would utilise the digital radio systems.

Since the contract was awarded, the parties have had to grapple with restrictions placed trade between the US and China. Tariffs imposed on Chinese exports would increase the uncertainty around the cost of the project, timelines, and effectiveness of the final solution.

“It is extremely unfortunate that the State Government’s project – which is limited to a radio network for train drivers and transit guards – has been caught up in the ongoing trade dispute between the US and China,” said Saffioti.

The WA government has indicated in a statement that it will continue with the project, although it will be delayed.

“Given the trade dispute, and the current economic and health crisis facing the world, the PTA has recommended a fresh approach for the radio replacement project,” said Saffioti.

“The PTA will continue its plans to deliver a new digital radio system for our expanding public transport system.”

Potential options include the withdrawal of Huawei Australia from the contract, or the termination of the contract as a whole. The PTA will look to preserve current subcontract arrangements.

The Australian Communications and Media Authority has extended the deadline for the PTA to vacate the analogue radio spectrum to beyond 2021.