North East Rail Line early works progressing

Investigation work has commenced towards the $235 North East Rail Line Upgrade project in Victoria, after the contract was awarded to John Holland last week.

Ninety kilometres of the 500 kilometres of track have been walked and site assessments are now underway. Site walks started at Albury and will continue south towards Melbourne.

According to ARTC, a team of up to five John Holland and Australian Rail Track Corporation (ARTC) project staff will be walking all 500 kilometres of track by mid-January, in preparation for the major works commencement in the new year.

Findings will inform site assessments about how  impacts to the community can be minimised.

Since October, early works have thus far included: 85 kilometres of tamping, the removal of over two kilometres of mudholes, and distribution of 6,500 tonnes of fresh ballast. Both tracks at the Summers Road level crossing in Springhurst have also be renewed.

“With our main works contractor in place, progress on the track upgrade will start to ramp up in the new year,” ARTC’s general manager for Victoria Projects Ed Walker said.

“Not only will people start to see increased activity in the rail corridor, but also John Holland and ARTC personnel out and about in local towns and businesses.”