Maintenance of Hunter network a reminder of level crossing safety

Coal Train Photo Hunter Valley Coal Chain Coordinator

Level crossings in the Hunter network are undergoing maintenance to improve safety for trains and motorists.

The Australian Rail Track Corporation (ARTC) is carrying out the works during a shutdown of the network from Newcastle to Ulan and Turrawan.

From September 22 to 25, 1,000 workers will conduct 500 maintenance jobs not limited to level crossings. These will include upgrading 3,500 metres of track, replacing 13,200 metres of rail, and regularly scheduled maintenance activities.

ARTC General Executive Hunter Valley Network Wayne Johnson said the level crossing work was in addition to regular maintenance.

“In the upcoming rail shutdown, in addition to our regular maintenance work, level crossings will be getting some special attention with tamping being carried out on 34 level crossings,” he said.

“A tamping machine is used to pack (or tamp) the track ballast under railway tracks to make the tracks more durable. The base of the level crossing is replaced and stabilised to improve the geometry of the track and this also helps improve the surface so vehicles will experience a smoother ride as a result.

“Tamping the levels crossings allows safer access across the railway crossings for vehicle traffic.”

Level crossings, of which only 21 per cent nationally are active, are a critical safety concern for the rail industry, and Johnson warned motorists of the consequences of not driving safely near level crossings.

“Tragically, every year too many people lose their lives in level crossing collisions, while there are more than 1,000 ‘near misses’ each year – the difference between a fatal collision and a near collision can be just seconds,” he said.

“With a bumper grain season ahead, we can expect high volumes of freight trains coming from the central areas of the state, so people need to be vigilant with level crossings in the regional parts of New South Wales.”

Maintenance is expected to finish on September 25.