KiwiRail is replacing sleepers, tracks and turnouts on the Auckland commuter network over the Christmas and New Year period, as part of a holiday work blitz, while further maintenance work will also go ahead across the Wellington passenger rail network.

In Wellington, the work includes installing the foundations for 60 new masts for the overhead power lines in the busiest part of the network – the approaches to Wellington Railway Station.

“Replacing the masts is not an easy task. Building new foundations for each of these requires a three-metre-deep hole. The masts date as far back as 1938, and need to be replaced,” KiwiRail’s chief operating officer capital projects David Gordon.

“It is just not possible to carry out that work while commuter services are running.”

“Already the network is delivering more than 14 million commuter trips a year to the 500,000 plus people who live in the region,” Gordon said.

“That is predicted to grow, and this work is needed to make that happen.”

“We’ll be taking advantage of the holiday lull, when passenger demand is down, to shut down big parts of the network and give our teams safe access to work on the line.”

KiwiRail is working on sites spread from the Wairarapa to the Hutt Valley and Porirua. Work includes building underpasses, upgrading level crossings and barriers, replacing rail and sleepers, and improving slope stability and drainage, along with the foundation work.

The work blitz is possible due to nearly $300 million that the government has slated to go towards modernisation and upgrades, alongside the usual annual maintenance.

Nearly 150 KiwiRail and NZTA staff and contractors will work on the Wellington line upgrades, while nearly 170 KiwiRail staff and contractors will take on the Auckland commuter network.

Auckland’s Western line will be closed to allow for works to replace sleepers, track and turnouts – which allow trains to change tracks – at several locations.

The Southern line and Eastern line will be closed south of Westfield for Otahuhu third platform work and the Puhinui interchange, track work and sleeper replacement between Papakura and Pukekohe. This includes four level crossings along the Western line and one on the Southern line.

“Working at level crossings also causes disruption to road networks, so it makes sense to take advantage of the holidays when both rail and road networks are quieter. This way we can carry out a lot of work with minimal disruption to commuters and road users,” KiwiRail executive general manager operations Siva Sivapakkiam said.

“Auckland is a busy network, with nearly 200,000 commuter services a year, and 246 freight services a week. That means a lot of wear and tear on the network. The maintenance we do now will help reduce delays and increase reliability in the future.”