Hunter network to remain closed; North Coast significantly damaged

rail damage - Transport NSW

After it originally thought it could re-open its Hunter Valley network as early as Thursday afternoon, the Australian Rail Track Corporation has announced the network will remain closed for at least 48 hours longer.

Re-opening of the ARTC’s North Coast network looks to be even further away, with significant damage recorded and crews scrambling just to get a grip on just how much repair work is needed.

The ARTC said on Wednesday night the Hunter Valley coal network was expected to re-open on Thursday afternoon, but warned that “the reopening [of the Hunter Valley network] remains contingent on improved weather conditions and receding water levels which continue to hamper repair works.”

It appears that those conditions did not improve for the ARTC overnight.

Due to high flood waters, the Maitland flood gates being closed and continued difficult conditions, the forecast for a return of Hunter Valley operations was revised on Thursday around noon, with a re-opening pushed back “an additional 48 hours at the earliest.”

The ARTC closed the Hunter and North Coast networks on Monday, due to  extreme weather and flooding in the region.

With the extended difficult conditions, the Hunter Valley network will remain closed now, meaning Hunter coal train, freight and passenger services remain suspended.

Re-opening of the North Coast network, which suffered major damage to its ballast at various points, looks to be even further away, however.

“The ARTC network along the mid-North Coast around Dungog remains closed and there is no current forecast for re-opening,” ARTC said on Wednesday.

“Initial track inspections indicate more than 18 sites have experienced significant washaways or landslips and each will require significant reinstatement works.”

ARTC confirmed on Thursday that its crews have now identified 22 work sites along the line, which require “significant repair works,” with “a large amount of track underwater”.

In one of those landslip sites, the ARTC said, a large embankment, approximately 8m high and 75m in length, washed out and across the rail line.

“The high water has compounded the response task and 14km of track between Paterson and Telarah is either under water or still unable to be inspected due to flooding and access being closed off (both on foot and by road),” the ARTC said.

“Given the nature and the extent of the damage ARTC is mobilising a dedicated project team to coordinate the repair and recovery efforts required. Project planning and sourcing equipment, material, supplies and other resources is underway.”

The ARTC said the damage to the rail line is believed to be worse than that of the 2007 floods in the same region.

“The scale of the response and high water levels mean ARTC is unable to provide a forecast for a return to operations for this section of the network.”